2024 © CPC Civils Ltd. All rights reserved.
Design by eSterling
£750,000
Amey & Yorkshire Water
Civil Engineering & Water Treatment Works
“Just a quick note to say thanks for taking the time to show us round last thursday- I was very impressed by the way that work at the site was being managed, so please pass my congratulation to the team” David Widdowson, Yorkshire Water
“A big thank you goes out to CPC regarding the Achilles audit undertaken yesterday, keep up the good work!” Andy Gustard, Batch Manager, Amey.
CPC Civils were appointed to construct a new build inlet works which would be integrated into the existing structure and included a motor control centre, washwater room, new screens, compactors, a Formula A overflow screen, drainage, road slabs, duct feeds and storm overflow pipework, to increase the capacity and efficiency of the Sewage Treatment Works.
The structure was designed in a way that meant CPC Civils could construct the build off line, with three final connections towards the end of the programme. This involved partial shutdowns and over pumping 400 litres per second of raw effluent.
CPC Civils were involved in the design process prior to contract award, and played a major role in phasing and redesigning parts of the structure to increase buildability, reduce materials usage and better the programme.
At CPC Civils request, drop beams were removed from the design in favour of additional columns, and movement joints were relocated to allow the three phases of the structure to be run concurrently.
The works carried out by CPC Civils used the following methods:
Ask a question