Normanton WTW

Project Value

£750,000

Client Name

Amey & Yorkshire Water

Project Type

Civil Engineering & Water Treatment Works

“Just a quick note to say thanks for taking the time to show us round last thursday- I was very impressed by the way that work at the site was being managed, so please pass my congratulation to the team” David Widdowson, Yorkshire Water

“A big thank you goes out to CPC regarding the Achilles audit undertaken yesterday, keep up the good work!” Andy Gustard, Batch Manager, Amey.

CPC Civils were successfully awarded the Normanton WTW contract in 2015 and completed works in 2016. Normanton Water Treatment Works is located adjacent to the Wakefield Europort, on the M62 Motorway, and has been in operation since the 1950’s.

CPC Civils were appointed to construct a new build inlet works which would be integrated into the existing structure and included a motor control centre, washwater room, new screens, compactors, a Formula A overflow screen, drainage, road slabs, duct feeds and storm overflow pipework, to increase the capacity and efficiency of the Sewage Treatment Works.

The structure was designed in a way that meant CPC Civils could construct the build off line, with three final connections towards the end of the programme. This involved partial shutdowns and over pumping 400 litres per second of raw effluent.

CPC Civils were involved in the design process prior to contract award, and played a major role in phasing and redesigning parts of the structure to increase buildability, reduce materials usage and better the programme.

At CPC Civils request, drop beams were removed from the design in favour of additional columns, and movement joints were relocated to allow the three phases of the structure to be run concurrently.

The works carried out by CPC Civils used the following methods:

  • Columns and shear walls were constructed using proprietary formwork systems;
  • Column boxes and pours were carried out using mechanical access, this reduced level of temporary works requirements and increase the safety of access and egress;
  • Suspended slabs were constructed using traditional prop and beam systems, due to the complex layout and level changes in the structure; and
  • Channel benching was achieved using traditional formwork.

Client Testimonials

“We have formed not only fantastic working relationships but also lasting friendships. I would not hesitate in working with CPC Civils again, as they are without question the most helpful, skilful and friendly partner you could wish for, and I look forward to developing this already fruitful relationship further in the coming years.”

“Well done Wayne Barron, John Donnellan, Pat Concannon, Conall Cunningham and the CPC team. We had a phone call from Paul Dennison (Severn Trent Water), he and his colleagues are very complimentary of the work at Kingsholm. They praised the tidiness, the setup, the workforce attitude and the standard of workmanship completed at the site ”

“I could sit and write multiple examples where CPC and your team have, in my opinion, gone above and beyond what would normally be expected. I would however just like to say that this ongoing attitude, and excellent working relationship, has not only aided Centro in 2 current Metro extensions it has also given me huge confidence in the planning of 5 further Metro extensions. It’s also made my job very enjoyable”

“Interesting weekend replacing a 12m length of sewer that had collapsed underneath a railway line in Bloxwich. Within 48 hours the team were able to diagnose the problem and work up a design and complete the repair. Amazing collaboration between STW, Amey, CPC and Network Rail”

Carillion have been impressed by the high safety, quality and overall standards of your on-site Supervision, quality of workmanship and the ability to complete the works in line with the agreed programme.  It has been a pleasure working with the team from CPC Civils on the Lower Don Valley Flood Defence Project and we welcome working with them once more on future successful projects

“Just a quick note to say thanks for taking the time to show us round last Thursday – I was very impressed by the way that work at the site was being managed, so please pass my congratulations on to the CPC team”

“A big thank you to the CPC team regarding the Achilles Audit undertaken on site – keep up the good work!”

“First and foremost, thanks to CPC for all the help and advice over the past 12 months. To each and every tradesman, your engineer, steelworkers, shuttering team, stone masons etc, a big thank you. At the risk of embarrassing anyone, we found everyone polite and obliging”

“I would like to thank all those who have worked on this project, especially the men who have been on site every day. In the 8 months of the work we have been kept fully informed at all times of the progress and all those concerned with the work have gone out of their way to be courteous and helpful.”

“Thanks to the installation teams from JP Concrete and CPC Civils  for a safe and excellent quality installation, very good job.”

“I am pleased to tell you that I have been asked by the Project Board to express their appreciation for the way you and your subcontractors have undertaken the District Heating Main Extension contract to date. We appreciate the professional manner in which you have proceeded with the planning and construction of the project despite the uncertain caused by delays in funding approval and agreements with landowners. The Board consider that your working methods, attention to detail, project management and health & saftey are excellent.”

“I would like to take this opportunity to thank you for the wonderful opportunity that you provided my students with last week. The effort, time and organisation that went into planning the visit is much appreciated. The resources you have given us are superb and will allow the students to really develop their understanding of flood management in their local area.”

Ask a question