Cooper Bridge Wier

Project Value

£2,000,000

Client Name

Kier

Project Type

Waterway Engineering

The scheme was constructed through one of the wettest years in Huddersfield’s history with several major floods to the river.  This did cause some challenges.  The workforce persevered and overcame these challenges to complete the new weir and fish pass and received the appreciation and recognition from the Canal and River Trust.

The purpose of the project was to reinstate the failed weir across the river Calder at Cooper Bridge near Mirfield. To comply with Environment Agency, it was also necessary to include a fish pass as part of the works.

Cooper Bridge Weir is located at Cooper Bridge Junction where the Huddersfield Broad canal joins the Calder and Hebble Navigation from the south. The function of the weir is to maintain the upstream water levels of the Calder and Hebble and the Huddersfield Broad canals.  Approximately two thirds of the original weir structure have failed in the past and had since been replaced with other materials over the years.

The principal structures to be constructed were a new 40m long reinforced concrete weir to replace the existing one and a Larinier fish pass and an elver pass. The weir included a concrete crest with steel sheet piles up and downstream tying into a sloping concrete apron to the upstream and a stepped concrete apron to the downstream.

The river Calder is a fast-flowing river which has a high flash flood risk.  Maintaining the flow of the river whilst constructing the new Weir and Fish Pass in the river was going to require advanced programming and temporary works installation.

For more information see the Canal and River Trusts article and waterways blog below.

The Project was split into 3 construction phases;

  • Install a sheet pile cofferdam a third of the way into the river to enable the Fish pass base to be constructed. Remove the section of the existing weir down to formation.  Continuous de-watering of the ground water and de-silting before discharging the clean ground water back into the River.  Once the reinforced base was constructed, remove sections of the upstream wall of the cofferdam to divert the river to flow through Phase 1.
  • Construct a temporary bridge capable of taking a 70ton crane and walkway over Phase 1 to enable the remnants of the weir to be removed and a stone causeway built out into the river. Install a large cofferdam the full width of the weir to allow the 40m long, 6 step reinforced concrete weir to be constructed one step at a time.  Construct new retaining wall and masonry wash wall.  Place Rip Rap anti scour stone downstream of the new weir.  Remove the sheet piled cofferdam to allow the river to flow over the new weir.
  • Close of the upstream wall of the Phase 1 cofferdam. Construct the new reinforced concrete fish pass and the remains of the weir.  The new Fish Pass incorporated an Elver pass as well as a Lariner pass with baffles and resting pool.  Install new fish monitoring equipment.  Remove the Phase 1 Cofferdam.  Landscaping to surrounding land and new fencing to the edge of the fish pass.

Client Testimonials

“We have formed not only fantastic working relationships but also lasting friendships. I would not hesitate in working with CPC Civils again, as they are without question the most helpful, skilful and friendly partner you could wish for, and I look forward to developing this already fruitful relationship further in the coming years.”

“Well done Wayne Barron, John Donnellan, Pat Concannon, Conall Cunningham and the CPC team. We had a phone call from Paul Dennison (Severn Trent Water), he and his colleagues are very complimentary of the work at Kingsholm. They praised the tidiness, the setup, the workforce attitude and the standard of workmanship completed at the site ”

“I could sit and write multiple examples where CPC and your team have, in my opinion, gone above and beyond what would normally be expected. I would however just like to say that this ongoing attitude, and excellent working relationship, has not only aided Centro in 2 current Metro extensions it has also given me huge confidence in the planning of 5 further Metro extensions. It’s also made my job very enjoyable”

“Interesting weekend replacing a 12m length of sewer that had collapsed underneath a railway line in Bloxwich. Within 48 hours the team were able to diagnose the problem and work up a design and complete the repair. Amazing collaboration between STW, Amey, CPC and Network Rail”

Carillion have been impressed by the high safety, quality and overall standards of your on-site Supervision, quality of workmanship and the ability to complete the works in line with the agreed programme.  It has been a pleasure working with the team from CPC Civils on the Lower Don Valley Flood Defence Project and we welcome working with them once more on future successful projects

“Just a quick note to say thanks for taking the time to show us round last Thursday – I was very impressed by the way that work at the site was being managed, so please pass my congratulations on to the CPC team”

“A big thank you to the CPC team regarding the Achilles Audit undertaken on site – keep up the good work!”

“First and foremost, thanks to CPC for all the help and advice over the past 12 months. To each and every tradesman, your engineer, steelworkers, shuttering team, stone masons etc, a big thank you. At the risk of embarrassing anyone, we found everyone polite and obliging”

“I would like to thank all those who have worked on this project, especially the men who have been on site every day. In the 8 months of the work we have been kept fully informed at all times of the progress and all those concerned with the work have gone out of their way to be courteous and helpful.”

“Thanks to the installation teams from JP Concrete and CPC Civils  for a safe and excellent quality installation, very good job.”

“I am pleased to tell you that I have been asked by the Project Board to express their appreciation for the way you and your subcontractors have undertaken the District Heating Main Extension contract to date. We appreciate the professional manner in which you have proceeded with the planning and construction of the project despite the uncertain caused by delays in funding approval and agreements with landowners. The Board consider that your working methods, attention to detail, project management and health & saftey are excellent.”

“I would like to take this opportunity to thank you for the wonderful opportunity that you provided my students with last week. The effort, time and organisation that went into planning the visit is much appreciated. The resources you have given us are superb and will allow the students to really develop their understanding of flood management in their local area.”

Ask a question