Bridge 34

Project Value

£400,000

Client Name

May Gurney

Project Type

Waterway Engineering

Bridge 34 is a public road bridge owned by Canal and River Trust over the North Oxford Canal.  The bridge was of a brick arch construction and was in a poor condition with large crack in the brick work wingwalls, pilaster and arch barrel.  The road surface was settling, and the parapet was missing many coping stones.

The principle features of the works were;

  • Setup of a full road closure of Brinklow Road
  • Install access structures to bridges faces.
  • Install support systems to services.
  • Removal of roadway and fill from abutments.
  • Crack stitching with Glass Fibre Reinforced Polymer anchors.
  • Drilling and installation of tie-bars and pattress plates right through the bridge structure to tie the wingwalls together.
  • Replacement and repointing of poor brickwork on the bridge faces with NHL 5 lime mortar.
  • Taking down and rebuilding of the southern parapet.
  • Installation of 2.4m sheet piles on the southern offside approach from the canal.
  • Installation of new reinforced concrete slab to the roadway, and ducting of the existing services.
  • Surfacing of the roadway and installation of road drainage.
  • Underpinning of the wingwalls with mass concrete.
  • Below water level brickwork repairs.

The bridge had a 10ton weight limit which restricted the size of plant we could use, and the canal needed to be kept open to allow boating traffic to continually navigate the canal.

The four wingwalls had to be tied to each other buy drilling right through the bridge from one side to the other and installing 6 stainless steel tie-bars and pattress plates.  The vast majority of the brickwork was then re-pointed with NHL5 lime mortar and new coping stones made and installed on the parapets.

The entire road surface and bridge deck was removed which involved excavating around live Gas and Water services.  A new reinforced concrete support slab was then installed followed by new kerb drainage and tarmac road surface.

Using specialist scaffolding, drilling rigs and floating plant the scheme was delivered on time and on budget to the delight and satisfaction of both Canal and River Trust and the County Council.

Client Testimonials

“We have formed not only fantastic working relationships but also lasting friendships. I would not hesitate in working with CPC Civils again, as they are without question the most helpful, skilful and friendly partner you could wish for, and I look forward to developing this already fruitful relationship further in the coming years.”

“Well done Wayne Barron, John Donnellan, Pat Concannon, Conall Cunningham and the CPC team. We had a phone call from Paul Dennison (Severn Trent Water), he and his colleagues are very complimentary of the work at Kingsholm. They praised the tidiness, the setup, the workforce attitude and the standard of workmanship completed at the site ”

“I could sit and write multiple examples where CPC and your team have, in my opinion, gone above and beyond what would normally be expected. I would however just like to say that this ongoing attitude, and excellent working relationship, has not only aided Centro in 2 current Metro extensions it has also given me huge confidence in the planning of 5 further Metro extensions. It’s also made my job very enjoyable”

“Interesting weekend replacing a 12m length of sewer that had collapsed underneath a railway line in Bloxwich. Within 48 hours the team were able to diagnose the problem and work up a design and complete the repair. Amazing collaboration between STW, Amey, CPC and Network Rail”

Carillion have been impressed by the high safety, quality and overall standards of your on-site Supervision, quality of workmanship and the ability to complete the works in line with the agreed programme.  It has been a pleasure working with the team from CPC Civils on the Lower Don Valley Flood Defence Project and we welcome working with them once more on future successful projects

“Just a quick note to say thanks for taking the time to show us round last Thursday – I was very impressed by the way that work at the site was being managed, so please pass my congratulations on to the CPC team”

“A big thank you to the CPC team regarding the Achilles Audit undertaken on site – keep up the good work!”

“First and foremost, thanks to CPC for all the help and advice over the past 12 months. To each and every tradesman, your engineer, steelworkers, shuttering team, stone masons etc, a big thank you. At the risk of embarrassing anyone, we found everyone polite and obliging”

“I would like to thank all those who have worked on this project, especially the men who have been on site every day. In the 8 months of the work we have been kept fully informed at all times of the progress and all those concerned with the work have gone out of their way to be courteous and helpful.”

“Thanks to the installation teams from JP Concrete and CPC Civils  for a safe and excellent quality installation, very good job.”

“I am pleased to tell you that I have been asked by the Project Board to express their appreciation for the way you and your subcontractors have undertaken the District Heating Main Extension contract to date. We appreciate the professional manner in which you have proceeded with the planning and construction of the project despite the uncertain caused by delays in funding approval and agreements with landowners. The Board consider that your working methods, attention to detail, project management and health & saftey are excellent.”

“I would like to take this opportunity to thank you for the wonderful opportunity that you provided my students with last week. The effort, time and organisation that went into planning the visit is much appreciated. The resources you have given us are superb and will allow the students to really develop their understanding of flood management in their local area.”

Ask a question