Mount Road,Stone

Project Value

£240,000

Client Name

Amey

Project Type

Civil Engineering

CPC have been working on and around water since the mid Nineties and as such have gained a vastly experienced workforce.

CPC Civils were successfully awarded the Mount Road, Stone contract in 2015 and completed works later that year. The project was to reline and refurbish a collapsing 225mm diameter storm sewer, which was approximately 140m in length, and to increase the system’s capacity by 66m3 to alleviate flooding in the area. The main lining works also included 12 lateral connections and 2 patch repairs.

CPC Civils completed all works in less than 12 weeks, in accordance with the Amey PLC’s timeframe, and provided a service that was within the client’s financial envelope.

An innovative offsite-constructed dual pipe turret was introduced on the Mount Road Project by CPC Civils, this lowered Amey PLC’s costs and increased onsite efficiency.

The project involved managing the issue of Mount Road vehicle access. Mount Road accommodates the Warburtons Ltd Depot which can only be accessed via the main road, subsequently Mouth Road could not be closed to the public to allow works to be undertaken. Furthermore, the final tie in man hole was 50 meters away from a National Rail main line crossing. To overcome the traffic management issue CPC Civils worked with A-Star Road Services Ltd to design a bespoke traffic light system which ensured cars would not back up towards the main line crossing during peak hours, this was agreed by all stakeholders including Network Rail. To allow the road to remain open to the public CPC Civils relined and scoured 140 meters of the 225mm diameter pipe with a Cured in Place Pipe Lining (CIPP), which allowed for smaller man hole entrance and exit points and subsequently enabled a minimum of 3.3 meters of carriage way to remain open.

Furthermore, the temporary works were designed around having 40 tonne wagons loading to the side of the excavation. To deliver the 66m3 outcome required, a larger 1.35-meter twin diameter pipe was laid over a shorter distance and using plastic piping which allows more clearance. The pipe had a pre-installed dry weather flow channel, was installed offline of the existing system, and tied in at either end to allow the increase in storage capacity to meet the client’s specification.

Client Testimonials

“We have formed not only fantastic working relationships but also lasting friendships. I would not hesitate in working with CPC Civils again, as they are without question the most helpful, skilful and friendly partner you could wish for, and I look forward to developing this already fruitful relationship further in the coming years.”

“Well done Wayne Barron, John Donnellan, Pat Concannon, Conall Cunningham and the CPC team. We had a phone call from Paul Dennison (Severn Trent Water), he and his colleagues are very complimentary of the work at Kingsholm. They praised the tidiness, the setup, the workforce attitude and the standard of workmanship completed at the site ”

“I could sit and write multiple examples where CPC and your team have, in my opinion, gone above and beyond what would normally be expected. I would however just like to say that this ongoing attitude, and excellent working relationship, has not only aided Centro in 2 current Metro extensions it has also given me huge confidence in the planning of 5 further Metro extensions. It’s also made my job very enjoyable”

“Interesting weekend replacing a 12m length of sewer that had collapsed underneath a railway line in Bloxwich. Within 48 hours the team were able to diagnose the problem and work up a design and complete the repair. Amazing collaboration between STW, Amey, CPC and Network Rail”

Carillion have been impressed by the high safety, quality and overall standards of your on-site Supervision, quality of workmanship and the ability to complete the works in line with the agreed programme.  It has been a pleasure working with the team from CPC Civils on the Lower Don Valley Flood Defence Project and we welcome working with them once more on future successful projects

“Just a quick note to say thanks for taking the time to show us round last Thursday – I was very impressed by the way that work at the site was being managed, so please pass my congratulations on to the CPC team”

“A big thank you to the CPC team regarding the Achilles Audit undertaken on site – keep up the good work!”

“First and foremost, thanks to CPC for all the help and advice over the past 12 months. To each and every tradesman, your engineer, steelworkers, shuttering team, stone masons etc, a big thank you. At the risk of embarrassing anyone, we found everyone polite and obliging”

“I would like to thank all those who have worked on this project, especially the men who have been on site every day. In the 8 months of the work we have been kept fully informed at all times of the progress and all those concerned with the work have gone out of their way to be courteous and helpful.”

“Thanks to the installation teams from JP Concrete and CPC Civils  for a safe and excellent quality installation, very good job.”

“I am pleased to tell you that I have been asked by the Project Board to express their appreciation for the way you and your subcontractors have undertaken the District Heating Main Extension contract to date. We appreciate the professional manner in which you have proceeded with the planning and construction of the project despite the uncertain caused by delays in funding approval and agreements with landowners. The Board consider that your working methods, attention to detail, project management and health & saftey are excellent.”

“I would like to take this opportunity to thank you for the wonderful opportunity that you provided my students with last week. The effort, time and organisation that went into planning the visit is much appreciated. The resources you have given us are superb and will allow the students to really develop their understanding of flood management in their local area.”

Ask a question