Irton Water Treatment Works

Project Value

£1,200,000

Client Name

Carillion

Project Type

Water Treatment Works

Scheme Overview

Due to deterioration in raw water quality and increased risk of pesticides within the raw water supply Irton Quality Scheme was developed and endorsed for construction. The scheme will provide pesticide removal and pH correction plant to achieve effective clarification and reduce Cryptosporidium risk.

CPC Civils were successfully awarded the Irton contract in 2016 and completed works in 2017. Due to deterioration in raw water quality and increased risk of pesticides within the raw water supply, the Irton Quality Scheme was developed and endorsed for construction. The scheme provided pesticide removal and pH correction plant to achieve effective clarification and reduce Cryptosporidium risk.

At contract award CPC Civils submitted tender programme was reviewed against final design drawings collaboratively by our management, commercial and site based team. During this review labour was allocated in line with revised structure delivery dates issued by the client to enable effective commissioning and optimisation of the plant.

During the initial Collaborative Planning Meeting, various items of work were highlighted to have process impact where shut downs of plant were required to be undertaken. To enable this CPC Civils developed a Process Impact Plan which then fed into Yorkshire Waters Key Asset Management Plan.

In addition to the principle contractor managing the project delivery risks, some of which CPC Civils had ownership of, CPC Civils also managed internal construction and business risks through regular Risk Meetings held during the course of the scheme. CPC Civils utilised the Risk Management Log which detailed the following:

  • What the risk is;
  • Whether it is financial, time related or both, including an assessment of cost and duration;
  • A detailed mitigation of that risk should it be necessary;
  • Risk Owner; and
  • Dates when the risk is likely to be realised in line with the programmed works.

CPC Civils managed cost using a ‘cost to complete’ excel spreadsheet, primarily this is updated by the Site Team on a weekly basis, with a monthly review by the Project Team. Any associated risk allocation was reduced, or added and a cost forecast report produced.

Yorkshire Water operatives were invited and attended meetings, during which any programme delivery issues that have been raised during the previous week were reviewed and next steps delegated (if these hadn’t already been resolved and closed by the team).

CPC Civils produced a monthly progress report which covers health and safety, quality, programme, design, cost and risk.

CPC Civils developed an inspection and test plan, prior to site start, which was approved by the principal contractor. This was followed, inspection sheets were completed and signed off for each element of work as the scheme progresses.

Client Testimonials

“We have formed not only fantastic working relationships but also lasting friendships. I would not hesitate in working with CPC Civils again, as they are without question the most helpful, skilful and friendly partner you could wish for, and I look forward to developing this already fruitful relationship further in the coming years.”

“Well done Wayne Barron, John Donnellan, Pat Concannon, Conall Cunningham and the CPC team. We had a phone call from Paul Dennison (Severn Trent Water), he and his colleagues are very complimentary of the work at Kingsholm. They praised the tidiness, the setup, the workforce attitude and the standard of workmanship completed at the site ”

“I could sit and write multiple examples where CPC and your team have, in my opinion, gone above and beyond what would normally be expected. I would however just like to say that this ongoing attitude, and excellent working relationship, has not only aided Centro in 2 current Metro extensions it has also given me huge confidence in the planning of 5 further Metro extensions. It’s also made my job very enjoyable”

“Interesting weekend replacing a 12m length of sewer that had collapsed underneath a railway line in Bloxwich. Within 48 hours the team were able to diagnose the problem and work up a design and complete the repair. Amazing collaboration between STW, Amey, CPC and Network Rail”

Carillion have been impressed by the high safety, quality and overall standards of your on-site Supervision, quality of workmanship and the ability to complete the works in line with the agreed programme.  It has been a pleasure working with the team from CPC Civils on the Lower Don Valley Flood Defence Project and we welcome working with them once more on future successful projects

“Just a quick note to say thanks for taking the time to show us round last Thursday – I was very impressed by the way that work at the site was being managed, so please pass my congratulations on to the CPC team”

“A big thank you to the CPC team regarding the Achilles Audit undertaken on site – keep up the good work!”

“First and foremost, thanks to CPC for all the help and advice over the past 12 months. To each and every tradesman, your engineer, steelworkers, shuttering team, stone masons etc, a big thank you. At the risk of embarrassing anyone, we found everyone polite and obliging”

“I would like to thank all those who have worked on this project, especially the men who have been on site every day. In the 8 months of the work we have been kept fully informed at all times of the progress and all those concerned with the work have gone out of their way to be courteous and helpful.”

“Thanks to the installation teams from JP Concrete and CPC Civils  for a safe and excellent quality installation, very good job.”

“I am pleased to tell you that I have been asked by the Project Board to express their appreciation for the way you and your subcontractors have undertaken the District Heating Main Extension contract to date. We appreciate the professional manner in which you have proceeded with the planning and construction of the project despite the uncertain caused by delays in funding approval and agreements with landowners. The Board consider that your working methods, attention to detail, project management and health & saftey are excellent.”

“I would like to take this opportunity to thank you for the wonderful opportunity that you provided my students with last week. The effort, time and organisation that went into planning the visit is much appreciated. The resources you have given us are superb and will allow the students to really develop their understanding of flood management in their local area.”

Ask a question