Birmingham City Centre Public Realm & Victoria Fountain Refurbishment

CPC Civils have been awarded by Birmingham City Council the ‘City Centre Public Realm’ project. CPC are delighted to be working with the City on this prestigious project, being a major contractor based in and around the city the scheme offers the opportunity to develop on long standing relationships in the City and give major social benefit throughout the span of the project. This multi-disciplined project has three key sections of works detailed below.

SECTION 3

January 2022 to August 2024

CPC Civils will be installing and upgrading the main public realm (Paving / lighting and street furniture) across the top of Victoria Square and the entirety of the Colmore Row and Waterloo Street Loop. The works will involve small teams removing the existing paving, upgrading the drainage systems and sub-base, and then installing a new paving across all these areas. CPC Civils will be conducting a full stakeholder engagement to ensure anyone that may be affected by these works are fully engaged with our works so we can adapt plans to minimise any disruption to businesses and the General Public. For further details please contact out stakeholder team on the details below.

1
1

New Paving across square

1
1

New paving and public realm works across Colmore road and down Waterloo Street

Upcoming Works and Areas Affected

Colmore Row road closure will start from 5th June 2023. The closure starts from Eversheds to Pieminister. Waterloo Street will become a 2-way street with a turning bay to allow for deliveries and drop offs, banksmen will be available to assist businesses with deliveries and drop offs throughout the closure. Access and egress for all businesses will still be accessible and walkways and footbridges will be installed where needed. The road closure will be in place till September 2023

Ask a question